File #: 23-0736    Version: 1 Name: Wadsworth Rd (IL Route 131 to Sheridan Rd) Phase II Agreement and Appropriation
Type: resolution Status: Passed
File created: 5/12/2023 In control: Public Works and Transportation Committee
On agenda: Final action: 6/13/2023
Title: Joint resolution authorizing an agreement with Ciorba Group, Inc., Chicago, Illinois, to provide Phase II professional engineering services for improvements along Wadsworth Road, from Illinois Route 131 to Sheridan Road, at a maximum cost of $3,048,093 and appropriating $3,658,000 of 1/4% Sales Tax for Transportation funds.
Attachments: 1. 23-0736 Consultant Agreement, Wadsworth Rd Phase II, 2. 23-0736 Vendor Disclosure, Ciorba, 3. 23-0736 Location Map, Wadsworth Road (IL 131 to Sheridan Road)

Title

Joint resolution authorizing an agreement with Ciorba Group, Inc., Chicago, Illinois, to provide Phase II professional engineering services for improvements along Wadsworth Road, from Illinois Route 131 to Sheridan Road, at a maximum cost of $3,048,093 and appropriating $3,658,000 of ¼% Sales Tax for Transportation funds.

 

Staff Summary

                     Ciorba Group, Inc., Chicago, Illinois, will be utilized to complete these Phase II design engineering services for improvements along Wadsworth Road from Illinois Route 131 to Sheridan Road. The improvements include pavement resurfacing, pavement widening to install a center two-way left turn lane, replacement of the existing Bull Creek culvert, replacement of existing retaining walls, and will include non-motorized improvements.

                     Lake County selects professional engineering firms in accordance with the Local Government Professional Services Selection Act, 50 ILCS 510/1 et. seq.

                     The Lake County Division of Transportation’s (LCDOT) Consultant Selection Process has been approved by the Federal Highway Administration and the Illinois Department of Transportation, and the firm selected for this project was selected in accordance with this approved process.

                     LCDOT received and evaluated Statements of Interest and Qualifications from 11 professional firms, of which three were short-listed and presented to a consultant selection committee.

                     This project is included in the Transportation Improvement Program, and is designated as Section 19-00055-08-RS.

 

Body

RESOLUTION

 

WHEREAS, Wadsworth Road, County Highway 17, from Illinois Route 131 to Sheridan Road, is a designated route on the County highway system; and

 

WHEREAS, Lake County believes it would be beneficial to the safety and welfare of the traveling public if Wadsworth Road, between Illinois Route 131 and Sheridan Road, could be improved inclusive of non-motorized improvements; and

 

WHEREAS, Phase II professional engineering services are required for these improvements; and

 

WHEREAS, it is recommended that a consultant engineering firm be employed to provide these Phase II professional engineering services; and

 

WHEREAS, Lake County, by and through its Division of Transportation, has selected a professional engineering services firm in accordance with the Local Government Professional Services Selection Act, 50 ILCS 510/1 et. seq.; and

 

WHEREAS, Ciorba Group, Inc., Chicago, Illinois, are consulting engineers skilled in the provision of said Phase II professional engineering services; and

 

WHEREAS, an appropriation of funds is required.

 

NOW, THEREFORE, BE IT RESOLVED, by this County Board of Lake County, Illinois, that the County Board Chair, the County Clerk, and the County Engineer of Lake County are authorized, and hereby directed to execute on behalf of Lake County, an agreement, and any amendments, between Lake County and Ciorba Group, Inc., Chicago, Illinois, at a maximum amount of $3,048,093, for Phase II professional engineering services for improvements along Wadsworth Road, between Illinois Route 131 and Sheridan Road, a draft copy of which is attached hereto; and

 

BE IT FURTHER RESOLVED, that the County Engineer shall transmit, in writing, the final agreement and any amendments, to be executed by the County Board Chair and the County Clerk; and

 

BE IT FURTHER RESOLVED, that there is hereby appropriated $3,658,000 of ¼% Sales Tax for Transportation funds for these Phase II professional engineering services, and designated as Section 19-00055-08-RS; and

 

BE IT FURTHER RESOLVED, that this agreement be administered in accordance with Chapter 605, Act 5, Section 5-205.2 of the Illinois Compiled Statutes without further Board action, providing the final contract cost chargeable under the funds appropriated does not exceed the appropriation.

 

DATED, at Waukegan, Illinois, on June 13, 2023.