Lake County, IL
File #: 09-1520    Version: 1 Name: 2009 Township Motor Fuel Tax; Newport Township Road District: Contract Award
Type: resolution Status: Passed
File created: 4/30/2009 In control: Public Works and Transportation Committee
On agenda: Final action: 5/12/2009
Title: Joint resolution authorizing a contract for hot mix asphalt removal and pavement resurfacing on Old Woodford Road from IL Rte. 173 to the cul-de-sac, 9th Street from Delany Road to Kilbourne Road and 21st Street from IL Rte. 173 to the cul-de-sac in Newport Township Road District and designated as Section 09-11101-00-GM, to Payne & Dolan, Inc. Antioch, Illinois in the amount of $285,871.45.
Title
Joint resolution authorizing a contract for hot mix asphalt removal and pavement resurfacing on Old Woodford Road from IL Rte. 173 to the cul-de-sac, 9th Street from Delany Road to Kilbourne Road and 21st Street from IL Rte. 173 to the cul-de-sac in Newport Township Road District and designated as Section 09-11101-00-GM, to Payne & Dolan, Inc. Antioch, Illinois in the amount of $285,871.45.
 
Staff Summary
·      2009 Township Motor Fuel Tax; Newport Township Road District: Contract Award.
·      A total of 3 bids were received and the lowest responsible bidder is Payne &  Dolan, Inc. Antioch, Illinois, in the amount of $285,871.45.
 
Body
R E S O L U T I O N
 
      WHEREAS, pursuant to authority granted by this Board of Lake County, the County Engineer heretofore called for sealed bids, by publication, for hot mix asphalt removal and pavement resurfacing on Old Woodford Road from IL Rte. 173 to the cul-de-sac, 9th Street from Delany Road to Kilbourne Road and 21st Street from IL Rte. 173 to the cul-de-sac in Newport Township Road District and designated as Section 09-11101-00-GM; and
 
      WHEREAS, pursuant to said publication and calling for said bids, sealed bids were received and opened on April 28, 2009, at 10:00 AM at the Lake County Division of Transportation in Libertyville, Illinois; a tabulation of said bids being as follows:
 
Payne & Dolan, Inc.
Antioch, IL
$285,871.45
 
Peter Baker & Son Co., Inc.
Lake Bluff, IL
$302,344.30
 
Curran Contracting
Crystal Lake, IL
$312,436.40
 
      WHEREAS, the Public Works and Transportation Committee, the County Engineer and the Purchasing Agent have examined each bid, and it appears that the lowest responsible bidder is Payne & Dolan, Inc., Antioch, Illinois their bid being $285,871.45, based on estimated quantities and unit prices; and
 
      NOW, THEREFORE BE IT RESOLVED by this County Board of Lake County that a contract be awarded to said Payne & Dolan, Inc.
Antioch, Illinois in accordance with their bid of $285,871.45 based on estimated quantities and unit prices and that the Purchasing Agent, the County Clerk, and the County Engineer of Lake County be authorized and they are hereby directed to enter into a contract with said low bidder for  hot mix asphalt removal and pavement resurfacing on Old Woodford Road from IL Rte. 173 to the cul-de-sac, 9th Street from Delany Road to Kilbourne Road and 21st Street from IL Rte. 173 to the cul-de-sac in Newport Township Road District and designated as Section 09-11101-00-GM.
 
      BE IT FURTHER RESOLVED that in as much as such estimated quantities are the best approximation that can be determined at this time, these quantities may be added to, deducted from, or modified from in the final determination of the contract cost in accordance with Chapter 605 of the Illinois Compiled Statutes, Act 5, Section 5-205.2 without further Board action, providing the final cost chargeable to the funds appropriated does not exceed the appropriation.
 
      BE IT FURTHER RESOLVED that this award be processed by the County Engineer for final approval of the Illinois Department of Transportation in accordance with the "Agreement of Understanding" between the Illinois Department of Transportation and Lake County, dated January 22, 2003.
 
 
Dated at Waukegan, Illinois, on this 12th day of May A.D., 2009