Title: Joint resolution authorizing an agreement with Civiltech Engineering, Inc., Itasca, Illinois, to provide combined Phase I and Phase II professional engineering services for intersection improvements at Darrell Road and Roberts Road, at a maximum cost of $1,517,304.53, and appropriating $1,822,000 of Motor Fuel Tax funds.
Attachments: 1. 26-0612 Consultant Agreement, 2. 26-0612 Vendor Disclosure, 3. 26-0612 Location Map

Title

Joint resolution authorizing an agreement with Civiltech Engineering, Inc., Itasca, Illinois, to provide combined Phase I and Phase II professional engineering services for intersection improvements at Darrell Road and Roberts Road, at a maximum cost of $1,517,304.53, and appropriating $1,822,000 of Motor Fuel Tax funds.

 

Staff Summary

                     These services include evaluating potential intersection improvements at Darrell Road and Roberts Road, including non-motorized improvements.

                     Lake County selects professional engineering firms in accordance with the Local Government Professional Services Selection Act, 50 ILCS 510/1 et. seq.

                     The Lake County Division of Transportation’s (LCDOT) Consultant Selection Process has been approved by the Federal Highway Administration and the Illinois Department of Transportation, and the firm selected for this project was selected in accordance with this approved process.

                     The selected firm has a satisfactory past relationship with the LCDOT.

                     This project is included in the Transportation Improvement Program and designated as Section 26-00177-04-CH.

 

Body

RESOLUTION

 

WHEREAS, Darrell Road, County Highway 44, and Roberts Road, County Highway 35, are designated routes on the county highway system; and

 

WHEREAS, Lake County believes it would be beneficial to the safety and welfare of the traveling public if the intersection at Darrell Road and Roberts Road could be improved, inclusive of non-motorized improvements; and

 

WHEREAS, combined Phase I and Phase II professional engineering services are required for these improvements; and

 

WHEREAS, it is recommended that a consultant engineering firm be employed to provide these professional engineering services; and

 

WHEREAS, Lake County, by and through its Division of Transportation, has selected a professional engineering services firm in accordance with the Local Government Professional Services Selection Act, 50 ILCS 510/1 et. seq.; and

 

WHEREAS, Civiltech Engineering, Inc., Itasca, Illinois, are consultant engineers skilled in the provision of said combined Phase I and Phase II professional engineering services; and

 

WHEREAS, Lake County, by and through its Division of Transportation, incurs other associated project costs and fees that are paid for outside of this engineering contract; and

 

WHEREAS, an appropriation of funds is required.

 

NOW, THEREFORE, BE IT RESOLVED, by this County Board of Lake County, Illinois, that the County Board Chair, the County Clerk, and the County Engineer of Lake County are authorized, and hereby directed to execute on behalf of Lake County, an agreement, and any amendments, between Lake County and Civiltech Engineering, Inc., Itasca, Illinois, at a maximum amount of $1,517,304.53, for combined Phase I and Phase II professional engineering services for intersection improvements at Darrell Road and Roberts Road, a draft copy of which is attached hereto; and

 

BE IT FURTHER RESOLVED, that the County Engineer shall transmit, in writing, the final agreement and any amendments, to be executed by the County Board Chair and the County Clerk; and

 

BE IT FURTHER RESOLVED, that there is hereby appropriated $1,822,000 of Motor Fuel Tax funds for these combined Phase I and Phase II professional engineering services and other associated project costs, and designated as Section 26-00177-04-CH; and

 

BE IT FURTHER RESOLVED, that this agreement be administered in accordance with Chapter 605, Act 5, Section 5-205.2 of the Illinois Compiled Statutes without further board action, providing the final contract cost chargeable under the funds appropriated does not exceed the appropriation; and

 

BE IT FURTHER RESOLVED, that the County Clerk is hereby directed to transmit four certified originals of this resolution to the district office of the Department of Transportation; and

 

BE IT FURTHER RESOLVED, that this appropriation be processed by the County Engineer for final approval on behalf of the Illinois Department of Transportation in accordance with the “Agreement of Understanding” between the Illinois Department of Transportation and Lake County, dated May 3, 2018.

 

DATED at Waukegan, Illinois, on June 9, 2026.