Title: Joint resolution authorizing a contract for the resurfacing of Gilmer Road from Diamond Lake Rd to IL Rte 83 and designated as Section 10-00079-15-RS, to Peter Baker & Son Co., Inc., Lake Bluff, IL in the amount of $347,994.49.
Attachments: 1. Bid Tabulation: 2010 Township Motor Fuel Tax; Gilmer Road Resurfacing: Contract Award
Title
Joint resolution authorizing a contract for the resurfacing of Gilmer Road from Diamond Lake Rd to IL Rte 83 and designated as Section 10-00079-15-RS, to Peter Baker & Son Co., Inc., Lake Bluff, IL in the amount of $347,994.49.
 
Staff Summary
·      Gilmer Road (Diamond Lake Rd to IL Rte 83) Resurfacing: Contract Award.
·      A total of 4 bids were received and the lowest responsible bidder is Peter Baker & Son
Co. Inc., Lake Bluff, IL in the amount of $347,994.49.
 
Body
R E S O L U T I O N
 
WHEREAS, pursuant to authority granted by this Board of Lake County, the County Engineer heretofore called for sealed bids, by publication, for the resurfacing of Gilmer Road (Diamond Lake Rd to IL Rte 83) and designated as Section 10-00079-15-RS; and
 
WHEREAS, pursuant to said publication and calling for said bids, sealed bids were received and opened on April 27, 2010, at 10:00 AM at the Lake County Division of Transportation in Libertyville, Illinois; a tabulation of said bids being as follows:
 
Peter Baker & Son Co., Inc.
Lake Bluff, IL
$347,994.49
 
Curran Contracting
Crystal Lake, IL
$368,389.44
 
Payne & Dolan, Inc.
Antioch, IL
$399,950.52
 
J. A. Johnson Paving Company
Arlington Heights, IL
$437,379.08
 
WHEREAS, the Public Works and Transportation Committee, the County Engineer and the Purchasing Agent have examined each bid, and it appears that the lowest responsible bidder is Peter Baker & Son Co., Inc., Lake Bluff, IL their bid being $347,994.49, based on estimated quantities and unit prices; and
 
WHEREAS, this County Board of Lake County, Illinois, by prior resolution at its meeting of February 9, 2010, appropriated $515,000.00 of Matching Tax funds to provide for the  resurfacing of Gilmer Road (Diamond Lake Rd to IL Rte 83) and designated as Section 10-00079-15-RS.    
 
NOW, THEREFORE BE IT RESOLVED by this County Board of Lake County that a contract be awarded to said Peter Baker & Son Co., Inc., Lake Bluff, IL in accordance with their bid of $347,994.49 based on estimated quantities and unit prices and that the Purchasing Agent, the County Clerk, and the County Engineer of Lake County be authorized and they are hereby directed to enter into a contract with said low bidder for the  resurfacing of Gilmer Road (Diamond Lake Rd to IL Rte 83) and designated as Section 10-00079-15-RS.
 
BE IT FURTHER RESOLVED that in as much as such estimated quantities are the best approximation that can be determined at this time, these quantities may be added to, deducted from, or modified from in the final determination of the contract cost in accordance with Chapter 605 of the Illinois Compiled Statutes, Act 5, Section 5-205.2 without further Board action, providing the final cost chargeable to the funds appropriated does not exceed the appropriations.
 
BE IT FURTHER RESOLVED that this award be processed by the County Engineer for final approval of the Illinois Department of Transportation in accordance with the "Agreement of Understanding" between the Illinois Department of Transportation and Lake County, dated January 22, 2003.
 
 